PMI PgMP Exam - Topic 6 Question 57 Discussion

An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.In what phase is the risk management plan created?
D) Program risk management planning
A) Program definition
B) Program execution management
C) Program delivery

PMI PgMP Exam - Topic 6 Question 57 Discussion

Actual exam question for PMI's PgMP exam
Question #: 57
Topic #: 6
[All PgMP Questions]

An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.

In what phase is the risk management plan created?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Sarah
7 months ago
Definitely D, it’s all about planning for risks upfront!
upvoted 0 times
...
Micheline
7 months ago
I thought risk management was ongoing, not just in one phase.
upvoted 0 times
...
Yoko
7 months ago
Wait, isn't that part of program execution too?
upvoted 0 times
...
Mona
8 months ago
Totally agree, it sets the foundation for everything!
upvoted 0 times
...
Earleen
8 months ago
Risk management plans are usually created in the program definition phase.
upvoted 0 times
...
Jaleesa
8 months ago
I’m leaning towards program delivery, but I recall something about risk management being more about planning than execution.
upvoted 0 times
...
Serina
8 months ago
I feel like it might be in the program risk management planning phase, but that seems too obvious, right?
upvoted 0 times
...
Arthur
8 months ago
I remember practicing a question about risk management, and I think it was related to program execution management.
upvoted 0 times
...
Louis
8 months ago
I think the risk management plan is created during the program definition phase, but I'm not entirely sure.
upvoted 0 times
...
Jess
8 months ago
Hmm, I'm not totally sure about this one. The question mentions "all guests", so I'm wondering if the answer could be A - Eight. But then again, it does say to upgrade them one by one. I'll have to re-read the question.
upvoted 0 times
...
Linette
8 months ago
I think the Import panel might be under the Insert tab? It seems like the right place for adding new content.
upvoted 0 times
...
Ramonita
8 months ago
I've got a good strategy for this. I'll recommend setting the maximum resource limit per group of databases and the maximum of Database Transaction Units to ensure the database can scale effectively.
upvoted 0 times
...
Linette
8 months ago
I think the key here is understanding that the null hypothesis represents no difference between the two conditions. So option A is the correct answer.
upvoted 0 times
...

Save Cancel