Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PgMP Exam - Topic 6 Question 107 Discussion

Actual exam question for PMI's PgMP exam
Question #: 107
Topic #: 6
[All PgMP Questions]

Your program has a budget at completion of $1,550,000 and is expected to last one year.

Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Tu
5 days ago
Yeah, SV of -$27,500 shows we're behind.
upvoted 0 times
...
Georgeanna
10 days ago
I feel like the schedule impacts everything more.
upvoted 0 times
...
Carissa
15 days ago
But the cost is also concerning. EAC is high.
upvoted 0 times
...
Bok
21 days ago
Agreed, SPI of .90 shows delays.
upvoted 0 times
...
Mose
26 days ago
I think the schedule is worse. SPI is low.
upvoted 0 times
...
Krissy
1 month ago
Definitely feels like the schedule is the bigger issue here.
upvoted 0 times
...
Haydee
1 month ago
Wait, how can both be bad? That seems off.
upvoted 0 times
...
Lashunda
2 months ago
Haha, this question is a real budget buster! Gotta love those vendor delays.
upvoted 0 times
...
Hubert
2 months ago
A) The schedule is performing worse because the SPI is .90. Sounds like a classic case of "running late and over budget."
upvoted 0 times
...
Roxane
2 months ago
B) The cost is performing worse because the EAC is $1,611,111. Looks like someone's been cooking the books!
upvoted 0 times
...
Renea
2 months ago
D) The cost is performing worse because the CPI is .96.
upvoted 0 times
...
Sueann
3 months ago
C) The schedule is performing worse because the SV is -$27,500.
upvoted 0 times
...
Paz
3 months ago
I recall that a CPI below 1 means cost overruns, so D might be the answer, but I'm not completely confident.
upvoted 0 times
...
Shanda
3 months ago
I practiced a question like this where negative SV indicated schedule delays, so I wonder if C could be right too.
upvoted 0 times
...
Lavonda
3 months ago
I'm not entirely sure, but I feel like the EAC being higher than the budget suggests cost problems, which might point to B being the answer.
upvoted 0 times
...
Aretha
3 months ago
I think I remember that the SPI being below 1 indicates schedule issues, so maybe A is correct?
upvoted 0 times
...
Casandra
3 months ago
Okay, I think I see it now. The SPI of .90 and the SV of -$27,500 both point to the schedule being the main problem, not the cost.
upvoted 0 times
...
Maira
4 months ago
I've got this! The SV is -$27,500, which means the schedule is performing worse. And the CPI of .96 indicates the cost is also not great, but the schedule is the bigger issue here.
upvoted 0 times
...
Kerry
4 months ago
I'm a bit confused on how to calculate the EAC. Is that the key to determining if the cost or schedule is performing worse?
upvoted 0 times
...
Norah
4 months ago
CPI of .96 means cost is slipping as well.
upvoted 0 times
...
Goldie
4 months ago
But the EAC shows we're over budget too!
upvoted 0 times
...
Lashanda
5 months ago
The SPI is .90, so yeah, schedule is lagging.
upvoted 0 times
...
Tresa
5 months ago
True, but CPI of .96 indicates cost issues too.
upvoted 0 times
...
Rolf
5 months ago
Okay, let me think this through step-by-step. The budget at completion is $1,550,000 and we've spent $725,000 so far, which is 45% complete. But we should be 50% complete by now, so the schedule is lagging.
upvoted 0 times
...
My
5 months ago
Hmm, this looks like a tricky one. I'll need to carefully calculate the SPI and CPI to determine which is performing worse.
upvoted 0 times
Yeah, but the cost isn't great either. CPI is under 1.
upvoted 0 times
...
Annita
4 months ago
I think the schedule is definitely behind. SPI is low.
upvoted 0 times
...
...

Save Cancel