A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.
What should the program manager do next to address this risk?
Reita
4 months agoCatarina
4 months agoDevora
4 months agoKerry
4 months agoLatrice
4 months agoMarkus
5 months agoJohnathon
5 months agoLavonna
5 months agoPaola
5 months agoDorsey
5 months agoSkye
5 months agoLazaro
5 months agoFrance
5 months ago