PMI PgMP Exam - Topic 5 Question 25 Discussion

Actual exam question for PMI's PgMP exam
Question #: 25
Topic #: 5
[All PgMP Questions]

A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.

What should the program manager do next to address this risk?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Reita
4 months ago
Updating the risk register is a must, but we need a solid plan first.
upvoted 0 times
...
Catarina
4 months ago
Wait, can they really just stop all change requests? That seems risky!
upvoted 0 times
...
Devora
4 months ago
Definitely need to prioritize resources, but option A is too vague.
upvoted 0 times
...
Kerry
4 months ago
I disagree, option C seems too harsh. We need flexibility!
upvoted 0 times
...
Latrice
4 months ago
Sounds like option B makes the most sense! Prioritize the critical change requests.
upvoted 0 times
...
Markus
5 months ago
I feel like we should be looking at the overall impact of change requests, so B might be the best choice. It aligns with what we practiced about managing risks effectively.
upvoted 0 times
...
Johnathon
5 months ago
I’m a bit torn between C and D. C seems too strict, but D doesn’t really address the immediate issue of delays. I guess I need to think more about the implications of each.
upvoted 0 times
...
Lavonna
5 months ago
I think B makes sense because it focuses on the critical change requests and also mentions updating the risk register, which we practiced in a similar scenario.
upvoted 0 times
...
Paola
5 months ago
I remember we discussed prioritizing resources based on impact analysis in class. It seems like A could be a good option, but I'm not entirely sure if that's enough.
upvoted 0 times
...
Dorsey
5 months ago
Wait, did they say 1-4 images? I'm a bit confused on the exact requirements here. I'll need to read the question more closely.
upvoted 0 times
...
Skye
5 months ago
This is a good one. I'm pretty confident I know the solution. The key is to add a deployment gate to the release pipeline that integrates with Azure Policy to validate the release before deployment. That way, the release won't be deployed unless it meets the policy requirements.
upvoted 0 times
...
Lazaro
5 months ago
Hmm, I'm a bit unsure about this one. I know there are a few different RPM commands, but I can't quite remember the exact one for updating a package. I'll have to think this through carefully.
upvoted 0 times
...
France
5 months ago
This looks like a tricky question. I'll need to carefully analyze the configurations and think through the requirements.
upvoted 0 times
...

Save Cancel