PMI PgMP Exam - Topic 5 Question 25 Discussion
A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.What should the program manager do next to address this risk?
B) Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register.
A) Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.
C) Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this.
D) Add the lack of skilled resources to facilitate the large number of change requests to the issue log.
Reita
10 months agoCatarina
11 months agoDevora
11 months agoKerry
11 months agoLatrice
11 months agoMarkus
11 months agoJohnathon
11 months agoLavonna
11 months agoPaola
11 months agoDorsey
12 months agoSkye
12 months agoLazaro
12 months agoFrance
12 months ago