Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PgMP Exam - Topic 5 Question 119 Discussion

Julie is the project manager of the NHQ Project. She and her project team have successfully finished the project and the customers have signed the project closure agreement. Julie has compiled all of the project records and the project's lessons learned documentation. What should Julie do with the project's lessons learned documentation?
D) These are transferred to the lessons learned knowledge base.
A) These are for Julie's reference when she is reviewed by the project sponsor.
B) These are given to the project sponsor so he can review the project.
C) These are given to the project steering committee so they may review the project performance.

PMI PgMP Exam - Topic 5 Question 119 Discussion

Actual exam question for PMI's PgMP exam
Question #: 119
Topic #: 5
[All PgMP Questions]

Julie is the project manager of the NHQ Project. She and her project team have successfully finished the project and the customers have signed the project closure agreement. Julie has compiled all of the project records and the project's lessons learned documentation. What should Julie do with the project's lessons learned documentation?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
I'm a bit confused about whether the project sponsor or the steering committee should get the lessons learned. I thought they both had different roles.
upvoted 0 times
...
Yvette
5 days ago
I remember a similar question where we discussed the importance of documenting lessons learned for future projects. I feel like option D makes the most sense.
upvoted 0 times
...
Wilda
10 days ago
I think the lessons learned should be transferred to a knowledge base, but I'm not entirely sure if that's the only option.
upvoted 0 times
...

Save Cancel