PMI PgMP Exam - Topic 5 Question 112 Discussion

Which one of the following is not an output of the direct and manage program execution process?
B) Program budget
A) Results of program work
C) Change requests
D) Request to terminate the program

PMI PgMP Exam - Topic 5 Question 112 Discussion

Actual exam question for PMI's PgMP exam
Question #: 112
Topic #: 5
[All PgMP Questions]

Which one of the following is not an output of the direct and manage program execution process?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Caren
4 days ago
I think the answer is B) Program budget.
upvoted 0 times
...
Blossom
9 days ago
D) Request to terminate the program seems off too.
upvoted 0 times
...
Serita
14 days ago
Definitely C) Change requests. They come from monitoring.
upvoted 0 times
...
Eileen
19 days ago
I agree, budgets are set before execution.
upvoted 0 times
...
Brynn
24 days ago
I think it's B) Program budget.
upvoted 0 times
...
Kara
30 days ago
D) Request to terminate the program seems off too.
upvoted 0 times
...
Evangelina
1 month ago
Definitely C) Change requests. They come from monitoring.
upvoted 0 times
...
Hildegarde
1 month ago
I agree, budgets are set before execution.
upvoted 0 times
...
Essie
2 months ago
I think it's B) Program budget.
upvoted 0 times
...
Santos
2 months ago
I thought results of program work were the main outputs!
upvoted 0 times
...
Rocco
2 months ago
Change requests definitely come out of that process.
upvoted 0 times
...
Dorian
2 months ago
Wait, are we sure about that? Seems off.
upvoted 0 times
...
Celestina
2 months ago
Totally agree, it's more of an input!
upvoted 0 times
...
Willard
2 months ago
I think the program budget is not an output.
upvoted 0 times
...
Margo
3 months ago
I thought the budget could change during execution, though.
upvoted 0 times
...
Yuonne
3 months ago
Change requests definitely come out of execution.
upvoted 0 times
...
Cecily
4 months ago
Wait, are you sure about that?
upvoted 0 times
...
Malcom
4 months ago
Totally agree, it's more of a planning tool.
upvoted 0 times
...
Dong
5 months ago
I think the program budget is not an output.
upvoted 0 times
...
Evangelina
5 months ago
I’m leaning towards D being the odd one out.
upvoted 0 times
...
Leslee
5 months ago
Change requests are definitely an output, right?
upvoted 0 times
...
Lisbeth
5 months ago
Wait, are you sure about that? I thought budgets were part of it.
upvoted 0 times
...
Maurine
5 months ago
Totally agree, it’s definitely not an output!
upvoted 0 times
...
Willow
5 months ago
I think the program budget is not an output.
upvoted 0 times
...
Aleisha
6 months ago
I’m leaning towards option B, but I could be mixing it up with other project management outputs.
upvoted 0 times
...
Sol
6 months ago
This question feels familiar; I think I practiced a similar one where we had to identify outputs from different processes.
upvoted 0 times
...
Denny
6 months ago
I'm not entirely sure, but I remember something about change requests being a common output in program execution.
upvoted 0 times
...
Oneida
6 months ago
I think the program budget might not be an output since it's more of an input for planning.
upvoted 0 times
...