New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PgMP Exam - Topic 4 Question 39 Discussion

Actual exam question for PMI's PgMP exam
Question #: 39
Topic #: 4
[All PgMP Questions]

Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week.

What must the new program manager do before program closure?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Christoper
4 months ago
Not sure if they can really pull this off in just a week.
upvoted 0 times
...
Merri
4 months ago
Working with the sponsor on benefits sustainment is crucial!
upvoted 0 times
...
Lorean
4 months ago
Wait, how can they close the program without reviewing the benefits plan first?
upvoted 0 times
...
Garry
4 months ago
I think starting closure right after the last launch is too rushed.
upvoted 0 times
...
Asuncion
4 months ago
Definitely need to collect lessons learned before closure.
upvoted 0 times
...
Andree
5 months ago
I think asking the steering committee for immediate closure might be risky. We should ensure everything is wrapped up properly first, right?
upvoted 0 times
...
Edda
5 months ago
I feel like working with the program sponsor to identify responsibilities for benefits sustainment is crucial, but I can't recall if that should happen before or after the last project goes live.
upvoted 0 times
...
Lilli
5 months ago
I remember a similar question where we had to consider stakeholder expectations. Reviewing the benefits management plan seems important, but I wonder if it’s too late for that now.
upvoted 0 times
...
Erick
5 months ago
I think the new program manager should definitely focus on collecting lessons learned, but I'm not sure if that should happen before the last project launch.
upvoted 0 times
...
Alesia
5 months ago
This looks like a straightforward OSPF configuration issue. I think matching the OSPF area between the two devices is the most likely solution.
upvoted 0 times
...
Daren
5 months ago
Okay, let's see. I think the key is to identify the two main levels where business continuity can be integrated. I'll review the options and try to eliminate the ones that don't fit.
upvoted 0 times
...
Bulah
5 months ago
This seems like a straightforward question about the purpose of a risk register. I'll review the options carefully and choose the one that best matches the description.
upvoted 0 times
...

Save Cancel