PMI PgMP Exam - Topic 4 Question 39 Discussion
Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week.What must the new program manager do before program closure?
D) Work with the program sponsor to identify who is responsible for benefits sustainment, and identify measures from the benefits management plan to measure success.
A) Review the benefits management plan to ensure that the first component project launched met stakeholder expectations.
B) Ask the program steering committee to allow program closure to start immediately following the launch of the last component project.
C) Begin to collect lessons learned from all stakeholders, and prepare mitigation strategies in advance of the last component project's launch.
Christoper
10 months agoMerri
11 months agoLorean
11 months agoGarry
11 months agoAsuncion
11 months agoAndree
11 months agoEdda
11 months agoLilli
11 months agoErick
11 months agoAlesia
12 months agoDaren
12 months agoBulah
12 months ago