Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 3 Question 76 Discussion

Actual exam question for PMI's PgMP exam
Question #: 76
Topic #: 3
[All PgMP Questions]

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind

schedule. Based on this information, what is the schedule performance index (SPI) for this program?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Kimbery
12 days ago
Is it just me, or does this program manager need to work on their time management skills? *shakes head* Gotta stay on top of those schedules, folks.
upvoted 0 times
...
Lizbeth
17 days ago
Piece of cake! The SPI is 0.86, and that's option D. *high-fives* These kinds of questions are my bread and butter.
upvoted 0 times
Bea
9 days ago
I think the SPI is 0.86, so option D is the correct answer.
upvoted 0 times
...
...
Muriel
1 months ago
Ah, I got it! The SPI is 0.86, which means the program is behind schedule. *chuckles* I wonder if the project manager is sweating bullets right now.
upvoted 0 times
Melynda
11 days ago
A) $821,065
upvoted 0 times
...
...
Twana
1 months ago
Wait, are we supposed to calculate the SPI or just identify it from the options? I better double-check the question.
upvoted 0 times
...
Delfina
1 months ago
I also believe the answer is B) .86, as the SPI indicates how efficiently the program is progressing in relation to the planned schedule
upvoted 0 times
...
Lauran
1 months ago
I agree with Shala, because SPI is calculated by dividing percent complete by percent planned, which in this case is 30% / 35% = .86
upvoted 0 times
...
Talia
1 months ago
Hmm, this seems straightforward. I'll go with option B, that's the schedule performance index (SPI) for this program.
upvoted 0 times
Britt
26 days ago
User 1: I think the SPI is .86
upvoted 0 times
...
...
Shala
2 months ago
I think the answer is B) .86
upvoted 0 times
...
Mitsue
2 months ago
I also believe the answer is B) .86, as the SPI indicates how efficiently the program is progressing compared to the planned schedule
upvoted 0 times
...
Reita
2 months ago
I agree with Vincent, because SPI is calculated by dividing percent complete by percent planned, which in this case is 30% / 35% = .86
upvoted 0 times
...
Vincent
2 months ago
I think the answer is B) .86
upvoted 0 times
...

Save Cancel