You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent
$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind
schedule. Based on this information, what is the schedule performance index (SPI) for this program?
Kimbery
12 days agoLizbeth
17 days agoBea
9 days agoMuriel
1 months agoMelynda
11 days agoTwana
1 months agoDelfina
1 months agoLauran
1 months agoTalia
1 months agoBritt
26 days agoShala
2 months agoMitsue
2 months agoReita
2 months agoVincent
2 months ago