The program sponsor returns from a board of directors meeting after identifying a significant risk to the program schedule. This may impact the program's benefits realization.What should the program manager do next?
D) Document the risk and create a mitigation plan.
A) Update the program benefits management plan and risk register.
B) Implement the mitigation plan for the identified risk.
C) Adjust the program scope to avoid the risk.