Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PgMP Exam - Topic 3 Question 110 Discussion

What does CPI value less than 1.0 indicates?
A) Cost overrun for work completed
B) Scheduled performance is great
C) Cost underrun of performance to date
D) Cost for completed work is as per estimate

PMI PgMP Exam - Topic 3 Question 110 Discussion

Actual exam question for PMI's PgMP exam
Question #: 110
Topic #: 3
[All PgMP Questions]

What does CPI value less than 1.0 indicates?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Roxane
1 month ago
I feel it's A, cost overrun for work completed.
upvoted 0 times
...
Dean
1 month ago
But isn't it also about performance?
upvoted 0 times
...
Leslie
1 month ago
Yeah, CPI less than 1.0 shows we're under budget.
upvoted 0 times
...
Ezekiel
2 months ago
I think it means cost underrun.
upvoted 0 times
...
Brynn
2 months ago
Nope, definitely cost overrun for work completed!
upvoted 0 times
...
Carli
2 months ago
Wait, are you sure? I thought it was about cost underrun.
upvoted 0 times
...
Ashley
2 months ago
I thought it could also mean good scheduling?
upvoted 0 times
...
Alease
2 months ago
Totally agree, it's a sign of overspending!
upvoted 0 times
...
Jerry
2 months ago
A CPI less than 1.0 means cost overrun.
upvoted 0 times
...
Valentin
3 months ago
A) Cost overrun for work completed
upvoted 0 times
...
Iraida
3 months ago
I thought a CPI less than 1.0 meant the project manager was cooking the books. Guess I've been watching too many crime shows!
upvoted 0 times
...
Carlota
3 months ago
D) Cost for completed work is as per estimate
upvoted 0 times
...
Tracie
4 months ago
The CPI value less than 1.0 indicates that the project is actually costing less than expected. That's like getting a discount on your project!
upvoted 0 times
...
Janessa
4 months ago
C) Cost underrun of performance to date
upvoted 0 times
...
Shaun
4 months ago
I’m really unsure about this one; I thought it could also relate to scheduled performance being great, but that doesn’t seem right now.
upvoted 0 times
...
Haydee
4 months ago
If I recall correctly, a CPI under 1.0 means costs are higher than planned, so it must be A.
upvoted 0 times
...
Bettina
4 months ago
I remember practicing a question like this, and I think it was about cost underrun, but that seems counterintuitive.
upvoted 0 times
...
Daniela
4 months ago
I think a CPI value less than 1.0 indicates a cost overrun, but I'm not entirely sure.
upvoted 0 times
...
Wynell
5 months ago
Alright, a CPI less than 1.0 means the cost for the completed work is less than the estimate. That's the definition of a cost underrun, so the correct answer is C) Cost underrun of performance to date. Nailed it!
upvoted 0 times
...
Pearlene
5 months ago
A CPI less than 1.0 means the cost for the completed work is less than the estimate. So that's a good thing - it indicates a cost underrun. I'm feeling pretty good about this one.
upvoted 0 times
...
Adelaide
5 months ago
Ugh, I'm a bit confused on this one. Is a CPI less than 1.0 good or bad? I know it has something to do with cost, but I can't remember if it's an overrun or underrun. Gotta think this through.
upvoted 0 times
...
Micaela
5 months ago
Okay, let's see. A CPI less than 1.0 means the cost for the completed work is less than the estimate, right? I'm pretty confident that's the right answer.
upvoted 0 times
...
Asha
5 months ago
Hmm, a CPI less than 1.0 - that's tricky. I think it indicates a cost underrun, but I'm not 100% sure. Gotta double-check that.
upvoted 0 times
Jutta
25 days ago
I believe it means a cost overrun for work completed.
upvoted 0 times
...
...

Save Cancel