U.S. Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PgMP Exam - Topic 2 Question 118 Discussion

During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.What should the program manager do?
B) Determine which component projects have excess capacity and rebalance those resources to the project that needs additional hours.
A) Communicate to the program sponsor regarding the additional estimated cost and request a change order.
C) Request that the project manager make the team members work additional hours and not bill the project.
D) Talk with the project manager and find ways to reduce hours in another part of the project.

PMI PgMP Exam - Topic 2 Question 118 Discussion

Actual exam question for PMI's PgMP exam
Question #: 118
Topic #: 2
[All PgMP Questions]

During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.

What should the program manager do?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel