PMI PgMP Exam - Topic 2 Question 115 Discussion

Posted by Lavera on May 05, 2026 at 09:14 AM

A program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced.

The program manager will use the qualified seller list to do which of the following?

Suggested Answer: D

Get Premium PgMP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
27 comments · newest first
MU
Muriel 11 days ago
Exactly, D is the priority here.
WI
Winfred 17 days ago
I just think they need to get proposals out first.
DO
Donette 22 days ago
A is also valid, but not the immediate next step.
LE
Leota 27 days ago
Yeah, D is the next step after the list.
WE
Wenona 1 month ago
I feel like D is the most direct action.
AN
Angelica 1 month ago
B could be important too, planning is key.
DA
Daron 1 month ago
True, but first they need to issue requests.
LO
Lorita 2 months ago
But what about A? They need to evaluate proposals too.
SV
Svetlana 2 months ago
Right, it’s about moving forward with the outsourcing.
AN
Anna 2 months ago
Exactly! D is the next step after having the list.
FA
Fabiola 2 months ago
Still, without proposals, how will they know who to choose?
SV
Svetlana 2 months ago
True, but B sets the foundation for the whole process.
AN
Anna 2 months ago
But they already have a qualified seller list. D is more direct.
FA
Fabiola 3 months ago
I’m leaning towards B. Preparing the procurement management plan is crucial.
KI
Kimi 3 months ago
I agree, D makes sense. Qualified sellers can submit.
SV
Svetlana 3 months ago
I agree, D makes sense. They need to find the right vendor.
AN
Anna 3 months ago
I think the answer is D. Issue requests for proposals.
TI
Timmy 3 months ago
I think it's D. They need proposals.
JI
Jina 3 months ago
I don't see how this relates to C) Perform the required program budget updates.
SH
Shoshana 4 months ago
Totally with you, Gabriele! D is the way to go!
SH
Shawna 4 months ago
Wait, can they really just outsource like that? Seems risky.
OL
Olga 4 months ago
I think it's more about A) Plan a proposal evaluation system.
GA
Gabriele 4 months ago
Definitely D) Issue requests for proposals. That's what the list is for!
SH
Sherell 4 months ago
I’m leaning towards option D, issuing requests for proposals, since that seems to align with what we learned about procurement processes.
WI
Winfred 6 months ago
I feel like the qualified seller list could help with proposal evaluation too, but I can't recall the exact context from my studies.
NO
Noemi 6 months ago
I remember practicing a question where we had to decide how to use a qualified seller list, and I think it was related to preparing procurement plans.
EN
Enola 6 months ago
I think the qualified seller list is mainly used for issuing requests for proposals, but I'm not entirely sure.