A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.
What should the program manager do next?
Bonita
9 months agoLeatha
9 months agoBrock
9 months agoNana
10 months agoSue
10 months agoPaz
10 months agoTyra
10 months agoMignon
11 months agoMaryanne
11 months agoTimothy
11 months agoDaniel
11 months agoRickie
11 months agoCecil
11 months agoCarissa
12 months agoMariann
12 months agoWhitley
12 months agoCherri
1 year agoJames
1 year agoMaddie
12 months agoMaryanne
12 months ago