PMI PgMP Exam - Topic 1 Question 92 Discussion
During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.What should the program manager do?
C) Request that the project manager make the team members work additional hours and not bill the project.
A) Communicate to the program sponsor regarding the additional estimated cost and request a change order.
B) Determine which component projects have excess capacity and rebalance those resources to the project that needs additional hours.
D) Talk with the project manager and find ways to reduce hours in another part of the project.
Solange
6 months agoElvis
6 months agoYoko
7 months agoTesha
7 months agoRickie
7 months agoJess
7 months agoSerina
8 months agoIvan
8 months agoOdelia
8 months agoCarin
8 months agoTy
8 months agoGlory
8 months agoLai
8 months agoMariann
1 year agoLashawn
11 months agoMariann
12 months agoFrederica
1 year agoReita
1 year agoFidelia
1 year agoNarcisa
1 year agoHillary
1 year agoMalinda
1 year agoDierdre
12 months agoAshlyn
1 year agoMalinda
1 year agoLeatha
1 year agoNobuko
1 year agoTimothy
1 year agoYvonne
1 year agoAhmad
1 year agoBrock
1 year agoRosendo
1 year ago