PMI PgMP Exam - Topic 1 Question 8 Discussion
The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff.What should the program manager do to ensure communications on the component projects are consistent?
B) Create a program communications management plan across all component projects.
A) Request a more experienced project manager to work on project B.
C) Direct all projects to use project A's communications management plan as a template.
D) Rework the communications management plans for all projects to be consistent.