I think the program manager should approve closure when the acceptance criteria are met, but I'm not entirely sure if that's the only factor to consider.
Okay, I've got this. The key is to focus on the component project, not the overall program. So the correct answer is when the project deliverables are complete, not the program deliverables. Easy!
Hmm, I'm a bit unsure about this one. Is it when the acceptance criteria are met, the project benefits are delivered, the program deliverables are complete, or the project deliverables are complete? I'll have to think through the differences between these options.
This seems like a straightforward question about project closure. I'll review the options carefully and think about the key criteria for closing a component project.
I'm a little confused by the wording here. Is there a difference between the project benefits being delivered and the acceptance criteria being met? I'll have to re-read the question and options carefully to make sure I understand.
Okay, I think I've got this. The key is that PAUSE frames are not forwarded by bridges or switches, so they don't generate any additional network traffic or information. I'm going with True on this one.
I'm with Darci on this one. D is the way to go. We don't want the program manager approving project closure before the actual work is done, do we? That would be a recipe for disaster.
You both make good points. But I'm going with C, when program deliverables are complete. The program manager is responsible for the overall program, not just the individual projects.
I disagree. I think the correct answer is B, when the project has delivered the project benefits. That's the whole point of the project, isn't it? To deliver the benefits, not just the deliverables.
I disagree. I think the correct answer is B, when the project has delivered the project benefits. That's the whole point of the project, isn't it? To deliver the benefits, not just the deliverables.
Hmm, this is a tricky one. I think the right answer is D, when project deliverables are complete. The project manager's job is to ensure the project is delivered, not necessarily the program benefits.
upvoted 0 times
...
Log in to Pass4Success
Sign in:
Report Comment
Is the comment made by USERNAME spam or abusive?
Commenting
In order to participate in the comments you need to be logged-in.
You can sign-up or
login
Lashawnda
3 months agoBelen
3 months agoAlpha
4 months agoCeleste
4 months agoJerry
4 months agoRemona
4 months agoStarr
4 months agoVashti
4 months agoLouis
5 months agoVallie
5 months agoEvangelina
5 months agoAmira
5 months agoDevon
5 months agoJill
5 months agoFannie
5 months agoShad
5 months agoLynsey
2 years agoGlory
2 years agoKeneth
2 years agoTashia
2 years agoAugustine
2 years agoAlayna
2 years agoDarci
2 years ago