Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 1 Question 70 Discussion

Actual exam question for PMI's Program Management Professional exam
Question #: 70
Topic #: 1
[All Program Management Professional Questions]

When should a program manager approve the closure of a component project?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Lynsey
25 days ago
I'm with Darci on this one. D is the way to go. We don't want the program manager approving project closure before the actual work is done, do we? That would be a recipe for disaster.
upvoted 0 times
...
Glory
26 days ago
You both make good points. But I'm going with C, when program deliverables are complete. The program manager is responsible for the overall program, not just the individual projects.
upvoted 0 times
...
Keneth
27 days ago
I disagree. I think the correct answer is B, when the project has delivered the project benefits. That's the whole point of the project, isn't it? To deliver the benefits, not just the deliverables.
upvoted 0 times
Tashia
11 days ago
B) When the project has delivered the project benefits
upvoted 0 times
...
Augustine
12 days ago
I disagree. I think the correct answer is B, when the project has delivered the project benefits. That's the whole point of the project, isn't it? To deliver the benefits, not just the deliverables.
upvoted 0 times
...
Alayna
13 days ago
A) When acceptance criteria of the project are met
upvoted 0 times
...
...
Darci
28 days ago
Hmm, this is a tricky one. I think the right answer is D, when project deliverables are complete. The project manager's job is to ensure the project is delivered, not necessarily the program benefits.
upvoted 0 times
...

Save Cancel