New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PgMP Exam - Topic 1 Question 70 Discussion

Actual exam question for PMI's PgMP exam
Question #: 70
Topic #: 1
[All PgMP Questions]

When should a program manager approve the closure of a component project?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Lashawnda
3 months ago
Closure should happen when program deliverables are complete too.
upvoted 0 times
...
Belen
3 months ago
Totally agree, project deliverables need to be complete first!
upvoted 0 times
...
Alpha
4 months ago
Wait, are we sure project deliverables are enough?
upvoted 0 times
...
Celeste
4 months ago
I think it should be after project benefits are delivered.
upvoted 0 times
...
Jerry
4 months ago
Definitely when acceptance criteria are met!
upvoted 0 times
...
Remona
4 months ago
I thought it was about project deliverables being complete, but now I'm questioning if that’s too narrow of a view.
upvoted 0 times
...
Starr
4 months ago
I feel like it could also be about the program deliverables being complete, but I can't recall if that's the main focus in this context.
upvoted 0 times
...
Vashti
4 months ago
I remember a practice question that emphasized the importance of project benefits being delivered, so I might lean towards option B.
upvoted 0 times
...
Louis
5 months ago
I think the program manager should approve closure when the acceptance criteria are met, but I'm not entirely sure if that's the only factor to consider.
upvoted 0 times
...
Vallie
5 months ago
Okay, I've got this. The key is to focus on the component project, not the overall program. So the correct answer is when the project deliverables are complete, not the program deliverables. Easy!
upvoted 0 times
...
Evangelina
5 months ago
Hmm, I'm a bit unsure about this one. Is it when the acceptance criteria are met, the project benefits are delivered, the program deliverables are complete, or the project deliverables are complete? I'll have to think through the differences between these options.
upvoted 0 times
...
Amira
5 months ago
This seems like a straightforward question about project closure. I'll review the options carefully and think about the key criteria for closing a component project.
upvoted 0 times
...
Devon
5 months ago
I'm a little confused by the wording here. Is there a difference between the project benefits being delivered and the acceptance criteria being met? I'll have to re-read the question and options carefully to make sure I understand.
upvoted 0 times
...
Jill
5 months ago
Okay, I think I've got this. The key is that PAUSE frames are not forwarded by bridges or switches, so they don't generate any additional network traffic or information. I'm going with True on this one.
upvoted 0 times
...
Fannie
5 months ago
This seems like a tricky question. I'll need to think through the different options carefully.
upvoted 0 times
...
Shad
5 months ago
Hmm, I'm a bit unsure about this one. Is the Cisco Secure Desktop feature also an option to consider?
upvoted 0 times
...
Lynsey
2 years ago
I'm with Darci on this one. D is the way to go. We don't want the program manager approving project closure before the actual work is done, do we? That would be a recipe for disaster.
upvoted 0 times
...
Glory
2 years ago
You both make good points. But I'm going with C, when program deliverables are complete. The program manager is responsible for the overall program, not just the individual projects.
upvoted 0 times
...
Keneth
2 years ago
I disagree. I think the correct answer is B, when the project has delivered the project benefits. That's the whole point of the project, isn't it? To deliver the benefits, not just the deliverables.
upvoted 0 times
Tashia
2 years ago
B) When the project has delivered the project benefits
upvoted 0 times
...
Augustine
2 years ago
I disagree. I think the correct answer is B, when the project has delivered the project benefits. That's the whole point of the project, isn't it? To deliver the benefits, not just the deliverables.
upvoted 0 times
...
Alayna
2 years ago
A) When acceptance criteria of the project are met
upvoted 0 times
...
...
Darci
2 years ago
Hmm, this is a tricky one. I think the right answer is D, when project deliverables are complete. The project manager's job is to ensure the project is delivered, not necessarily the program benefits.
upvoted 0 times
...

Save Cancel