Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?
D) Interface management plan
A) Stakeholder management plan
B) Communications management plan
C) Human resource management plan

PMI PgMP Exam - Topic 1 Question 121 Discussion

Actual exam question for PMI's PgMP exam
Question #: 121
Topic #: 1
[All PgMP Questions]

Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Shoshana
2 days ago
I'm not entirely sure, but I remember something about a Communications management plan being related to interactions too.
upvoted 0 times
...
Charlene
7 days ago
I think Holly is working on the Stakeholder management plan since it involves identifying who the program needs to interact with.
upvoted 0 times
...