PMI PfMP Exam - Topic 8 Question 17 Discussion
Roadmaps may be prepared to show different elements, and at the beginning they may not provide details of the various components. As a high-level plan at the portfolio level, the roadmap:
A) Identifies internal and external dependencies
B) Serves as a master schedule to show the timing of approved components
C) Contains all the details of program and project roadmaps
D) Serves to identify issues