Assume the organization's strategy has undergone a significant change, and as a result the mix of components in the portfolio also will change. As the portfolio manager, you need to update your charter in order to reflect:
D) Key stakeholders
A) The new 'to be' vision
B) Interdependencies between the new components
C) Risk tolerances

PMI PfMP Exam - Topic 8 Question 106 Discussion

Actual exam question for PMI's PfMP exam
Question #: 106
Topic #: 8
[All PfMP Questions]

Assume the organization's strategy has undergone a significant change, and as a result the mix of components in the portfolio also will change. As the portfolio manager, you need to update your charter in order to reflect:

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Andra
2 days ago
I think we practiced a question about interdependencies before, and it was tricky to identify all the connections between components. I hope I can remember the key points.
upvoted 0 times
...
Ben
7 days ago
I remember discussing how important it is to align the portfolio charter with the new vision, but I'm not entirely sure how to articulate that change clearly.
upvoted 0 times
...

Save Cancel