PMI PfMP Exam - Topic 6 Question 20 Discussion
After the stakeholder analysis is complete, a best practice is to put stakeholders into a matrix to develop a communications management strategy. A simple but useful approach is to set it up to show:
D) Level of influence and level of interest
A) Level of authority and level of interest
B) Level of authority and level of involvement
C) Level of influence and level of impact
Noel
7 months agoJoseph
7 months agoAmie
7 months agoTwila
8 months agoAudry
8 months agoDelmy
8 months agoKrissy
8 months agoGeorgeanna
8 months agoRoxane
8 months agoAndrew
8 months agoTommy
8 months agoSherita
8 months ago