PMI PfMP Exam - Topic 6 Question 104 Discussion

As you work to determine which of four possible components to optimize the portfolio, assume you are using the internal rate of return as the key crite rion to make your recommendation. Only one new component can be added based on financial constraints. Each of the four potential components has benefits that support the strategic plan. Based on the following data, you recommend:
C) Program B
A) Project A
B) Program A
D) Project B

PMI PfMP Exam - Topic 6 Question 104 Discussion

Actual exam question for PMI's PfMP exam
Question #: 104
Topic #: 6
[All PfMP Questions]

As you work to determine which of four possible components to optimize the portfolio, assume you are using the internal rate of return as the key crite rion to make your recommendation. Only one new component can be added based on financial constraints. Each of the four potential components has benefits that support the strategic plan. Based on the following data, you recommend:

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Edelmira
3 days ago
Program A has solid benefits too, don’t overlook it!
upvoted 0 times
...
Merri
8 days ago
Totally agree, Project A is the way to go!
upvoted 0 times
...
Ronald
13 days ago
Wait, how can we be sure these numbers are accurate?
upvoted 0 times
...
Latricia
19 days ago
I think Program B could be a better fit for long-term goals.
upvoted 0 times
...
Remona
24 days ago
Project A has the highest IRR, makes sense!
upvoted 0 times
...
Lon
29 days ago
I think we looked at a case where optimizing for IRR led to unexpected choices. I want to say Project B could be the right pick, but I need to remember the specific data points we analyzed.
upvoted 0 times
...
Levi
1 month ago
I’m a bit confused about how to weigh the benefits of each component against their IRR. I feel like Program B could be a strong contender, but I’m not entirely confident.
upvoted 0 times
...
Xenia
1 month ago
This question feels similar to the practice ones where we had to choose between projects based on their financial metrics. I think Project A might be the best option, but I need to double-check the numbers.
upvoted 0 times
...
Denny
1 month ago
I remember we discussed how the internal rate of return is crucial for evaluating project viability, but I'm not sure which component has the highest IRR here.
upvoted 0 times
...