Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PfMP Topic 3 Question 54 Discussion

Actual exam question for PMI's Portfolio Management Professional exam
Question #: 54
Topic #: 3
[All Portfolio Management Professional Questions]

As soon as you complete the portfolio risk management plan, and you have been working on it now with a team, you realize you need to update some organizational process assets such as:

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Elli
25 days ago
You know, I was just thinking the same thing. The lessons learned are crucial for improving our risk management process going forward. I'd go with C) Lessons learned as the answer.
upvoted 0 times
Goldie
8 days ago
Agreed, let's prioritize updating the lessons learned as part of our risk management plan.
upvoted 0 times
...
Precious
9 days ago
True, but ultimately, lessons learned will provide us with valuable insights for future projects.
upvoted 0 times
...
Gearldine
10 days ago
Having a risk interview guide will help us gather more detailed information from stakeholders.
upvoted 0 times
...
Lynna
11 days ago
Let's not forget to update the risk register with any new risks identified.
upvoted 0 times
...
Annita
12 days ago
We should also update our risk checklists to ensure we are capturing all potential risks.
upvoted 0 times
...
Raul
13 days ago
I agree, lessons learned are key for continuous improvement.
upvoted 0 times
...
...
Ming
26 days ago
Hmm, I'm not so sure. While the risk register is important, I think the lessons learned might be even more relevant here. After going through the portfolio risk management plan, we'd want to document what went well, what didn't, and how we can improve next time.
upvoted 0 times
...
Bette
27 days ago
I agree, this is a tough one. The portfolio risk management plan is all about identifying, analyzing, and planning for risks, so I'm leaning towards B) Risk register as the answer. That's where we'd capture all the risks we've identified.
upvoted 0 times
...
Pete
28 days ago
This is a tricky one. I'm not sure if the correct answer is B) Risk register or C) Lessons learned. I think we need to consider what kind of organizational process assets are typically updated after completing a portfolio risk management plan.
upvoted 0 times
...

Save Cancel