Assume you are preparing the first portfolio risk management plan for your outsourcing company, which typically handles call centers around the world. While the company has implemented portfolio management and has a Portfolio Oversight Group, it did not previously assess risks to the portfolio itself. Instead, it assumed risks would be managed at the project level. However, numerous customer complaints have been received. The root cause is once a new call center is established, limited if any planning is done as the manager rushes to have it ready and operational as soon as possible. This has led to a lack of understanding as to what is required for the call centers to be successful. In preparing this plan, you are reviewing the portfolio management plan because it: