Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam CAPM Topic 9 Question 89 Discussion

Actual exam question for PMI's CAPM exam
Question #: 89
Topic #: 9
[All CAPM Questions]

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Ollie
13 days ago
I'm just hoping the answer isn't 'All of the above' - that would be a real mind-bender!
upvoted 0 times
...
Brandon
27 days ago
D) To-complete performance makes the most sense to me. Gotta love these tricky project management questions!
upvoted 0 times
Dorothy
7 days ago
C) Schedule performance
upvoted 0 times
...
Irene
10 days ago
B) Cost performance
upvoted 0 times
...
Kent
21 days ago
A) Estimate at completion
upvoted 0 times
...
...
Kirk
1 months ago
Hmm, I'm leaning towards A) Estimate at completion. Isn't that the overall projected cost of the project based on the current performance?
upvoted 0 times
...
Kasandra
1 months ago
I'd go with B) Cost performance. Isn't that the index that measures how efficiently we're using our resources?
upvoted 0 times
...
Glory
1 months ago
I'm not sure, but I think it could also be A) Estimate at completion.
upvoted 0 times
...
Lamonica
1 months ago
D) To-complete performance seems like the correct answer here. It's the calculated projection of the cost performance needed to meet the management goal.
upvoted 0 times
Aimee
6 days ago
D) To-complete performance seems like the correct answer here. It's the calculated projection of the cost performance needed to meet the management goal.
upvoted 0 times
...
Leota
7 days ago
D) To-complete performance
upvoted 0 times
...
Rosita
11 days ago
C) Schedule performance
upvoted 0 times
...
Sylvie
15 days ago
B) Cost performance
upvoted 0 times
...
Herminia
29 days ago
A) Estimate at completion
upvoted 0 times
...
...
Andree
1 months ago
I agree with Val. To-complete performance makes sense for that question.
upvoted 0 times
...
Val
2 months ago
I think the answer is D) To-complete performance.
upvoted 0 times
...

Save Cancel