Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam CAPM Topic 6 Question 79 Discussion

Actual exam question for PMI's CAPM exam
Question #: 79
Topic #: 6
[All CAPM Questions]

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Franchesca
8 days ago
I don't know, man. I'm just here for the free donuts. What's this about three-point estimating? Can I use that to estimate how many donuts I can eat in one sitting?
upvoted 0 times
...
Lavina
11 days ago
This is easy! The expected duration is the average of the three estimates. So, (2 + 4 + 12) / 3 = 6 months. Wait, that's not one of the options. I guess I'll just go with C - five months.
upvoted 0 times
...
Nettie
12 days ago
Hold on, isn't the three-point estimating technique supposed to give us a more accurate estimate? I'm going to have to do some calculations on this one. Hmm, I'll go with option D - twelve months. Better safe than sorry, right?
upvoted 0 times
...
Jesusita
23 days ago
Okay, let's think this through. The most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year. I'm going to go with option C - five months. That sounds about right.
upvoted 0 times
Rosendo
5 days ago
I agree, option C - five months seems like the right choice.
upvoted 0 times
...
Rueben
11 days ago
I think the expected duration is five months.
upvoted 0 times
...
...
Natalie
1 months ago
This is a trick question! The expected duration is clearly not two months, four months, or even twelve months. Whoever came up with this needs to go back to school.
upvoted 0 times
Arminda
21 days ago
The expected duration is calculated as (optimistic + 4 * most likely + pessimistic) / 6
upvoted 0 times
...
Arminda
24 days ago
Five
upvoted 0 times
...
...
Luisa
2 months ago
I agree with Linn, the expected duration should be four months based on the three-point estimating technique.
upvoted 0 times
...
Linn
2 months ago
I believe it is four months because that's the most likely duration.
upvoted 0 times
...
Adelaide
2 months ago
I think the expected duration is five months.
upvoted 0 times
...

Save Cancel