PMI CAPM Exam - Topic 6 Question 14 Discussion

When managing costs in an agile environment, what should a project manager consider?
A) Lightweight estimation methods can be used as changes arise.
B) Agile environments make cost aggregation more difficult.
C) Agile environments make projects more costly and uncertain.
D) Detailed cost calculations benefit from frequent changes.

PMI CAPM Exam - Topic 6 Question 14 Discussion

Actual exam question for PMI's CAPM exam
Question #: 14
Topic #: 6
[All CAPM Questions]

When managing costs in an agile environment, what should a project manager consider?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Loise
7 months ago
Not sure about that, changes can also lead to chaos in budgeting.
upvoted 0 times
...
Stephaine
7 months ago
Frequent changes can really help refine cost calculations.
upvoted 0 times
...
Karan
7 months ago
Surprised to see people think agile makes projects more costly!
upvoted 0 times
...
Tarra
8 months ago
I disagree, cost aggregation isn't that hard if you plan well.
upvoted 0 times
...
Kiley
8 months ago
Lightweight estimation methods are definitely a plus!
upvoted 0 times
...
Winifred
8 months ago
I recall that detailed cost calculations might not benefit from frequent changes, so D seems off to me.
upvoted 0 times
...
Jettie
8 months ago
I practiced a question similar to this, and I think C is misleading; agile can actually help manage costs better if done right.
upvoted 0 times
...
Tonette
8 months ago
I remember discussing how lightweight estimation methods can help adapt to changes, so I think A might be correct.
upvoted 0 times
...
Carey
8 months ago
I'm not entirely sure, but I feel like cost aggregation could be tricky in agile, which makes B a possibility.
upvoted 0 times
...
Kara
8 months ago
Based on my understanding of the Business Manager tool, I believe the correct answer is A. The Import & Export module is typically used to bring in static assets like images, rather than dynamic product or content data. But I'll double-check the documentation to be sure.
upvoted 0 times
...
Mabel
8 months ago
Hmm, this seems like a tricky one. I know that Docker has some built-in security features, but I'm not sure if the `--encrypted` flag is specifically for encrypting overlay traffic. I'll need to think this through carefully and maybe do a quick search to see if I can find any examples or documentation on this.
upvoted 0 times
...
Quentin
8 months ago
Hmm, I'm not sure about this one. I know Cosmos DB has different replication and consistency options, but I'm not totally clear on how Availability Zones fit in. I'll have to think this through carefully.
upvoted 0 times
...

Save Cancel