PMI CAPM Exam - Topic 4 Question 9 Discussion
A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
D) Perform Integrated Change Control
A) Monitor and Control Project Work
B) Direct and Manage Project Work
C) Close Project or Phase