PMI Exam CAPM Topic 4 Question 58 Discussion

Actual exam question for PMI's Certified Associate in Project Management exam
Question #: 58
Topic #: 4
[All Certified Associate in Project Management Questions]

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Show Suggested Answer Hide Answer
Suggested Answer: D