Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI CAPM Exam - Topic 4 Question 112 Discussion

Posted by Aleisha on May 26, 2026 at 09:52 AM

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3

Suggested Answer: D

This question utilizes the Earned Schedule (ES) method, which is an extension of the traditional Earned Value Management (EVM) framework. While traditional EVM measures schedule variance in currency (dollars/units), Earned Schedule measures it in units of time.

According to the PMI Practice Standard for Earned Value Management and references in the PMBOK Guide:

Identify the Variables:

Earned Schedule (ES): 16 weeks. (Note: In this specific calculation context, 'ES' refers to Earned Schedule---the duration that should have been taken to achieve the current earned value---rather than 'Early Start').

Actual Time (AT): 12 weeks.

Schedule Performance Index (SPI): 1.3 (given).

Formula for Schedule Variance (Time):

The formula for Schedule Variance in terms of time ($SV_t$) is:

$$SV_t = ES - AT$$

Substituting the given values:

$$SV_t = 16 - 12 = 4$$

Validation with SPI:

The formula for the Schedule Performance Index in terms of time ($SPI_t$) is:

$$SPI_t = ES / AT$$

Substituting the values:

$$SPI_t = 16 / 12 = 1.33...$$

This matches the provided SPI of 1.3 (rounded to one decimal place), confirming that the interpretation of the variables is correct.

Conclusion:

A positive Schedule Variance of 4 indicates that the project is 4 weeks ahead of schedule. This is consistent with an SPI greater than 1.0 (1.3), which denotes efficient schedule performance.


Get Premium CAPM Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
21 comments · newest first
BE
Bettye 27 days ago
Same here, let’s verify!
RH
Rhea 1 month ago
I’ll calculate again.
VI
Viola 1 month ago
Good idea! We need to be sure.
PA
Paulene 1 month ago
Let’s double-check the formulas!
BE
Bettye 2 months ago
I see your point, but I still think C is more accurate.
RH
Rhea 2 months ago
I’m going with D. It seems right based on my calculations.
VI
Viola 2 months ago
Because SV = EV - PV, and it fits the numbers.
PA
Paulene 2 months ago
Why C?
VI
Viola 2 months ago
I’m leaning towards option C.
BE
Bettye 2 months ago
I feel confident about calculating SV.
RH
Rhea 3 months ago
I think the SPI helps a lot.
PA
Paulene 3 months ago
This question is tricky!
CU
Curtis 3 months ago
5 seems way too high, not buying it.
CO
Colby 3 months ago
Totally agree with Floyd on this one!
CA
Catalina 3 months ago
Wait, how does SPI of 1.3 fit in?
FL
Floyd 3 months ago
I think it's option C, 3.
AL
Alesia 4 months ago
SV is calculated as EV - PV.
CH
Cheryl 4 months ago
I think the answer might be 3, but I’m not confident. I remember we did a problem where we had to find SV, and I got mixed up with the formulas.
RO
Ronnie 4 months ago
I feel like I might need to calculate the earned value first, but I’m confused about how to do that with the early start date.
CE
Celestina 4 months ago
I remember something about the SPI being related to schedule variance, but I can't recall how to apply it here. Did we practice a similar question in class?
SH
Sheron 4 months ago
I think the schedule variance is calculated using the formula SV = EV - PV, but I'm not entirely sure how to find those values from the given data.
0/2000 characters

Save Cancel