PMI Exam CAPM Topic 3 Question 91 Discussion

Actual exam question for PMI's CAPM exam
Question #: 91
Topic #: 3
[All CAPM Questions]

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Beata
3 hours ago
I'm leaning towards A) Influence/impact grid. It's similar to the power/interest model, but focuses more on the overall impact of the stakeholders.
upvoted 0 times
...
Gladys
3 days ago
Ah, this one's tricky! I'm going to go with B) Power/influence grid. It's a classic stakeholder analysis tool, and it takes both power and influence into account.
upvoted 0 times
...
Nikita
19 days ago
Hmm, I'm not sure. Could it be D) Salience model? That seems to take into account both power and interest, which is what the question is asking for.
upvoted 0 times
Joni
9 days ago
I agree, the Salience model seems to be the best fit for grouping stakeholders based on their authority and concern.
upvoted 0 times
...
Reynalda
15 days ago
I think you might be right. The Salience model does consider both power and interest.
upvoted 0 times
...
...
Tu
23 days ago
I think the answer is C) Power/interest grid. Grouping stakeholders by their authority and concern seems to fit this model best.
upvoted 0 times
...
Talia
1 months ago
I'm not sure, but I think D) Salience model could also be a possible answer. It focuses on the importance of stakeholders.
upvoted 0 times
...
Skye
1 months ago
I agree with Lavelle. Stakeholders are classified based on their power and interest in the project outcomes.
upvoted 0 times
...
Lavelle
2 months ago
I think the answer is C) Power/interest grid.
upvoted 0 times
...