Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam CAPM Topic 3 Question 67 Discussion

Actual exam question for PMI's Certified Associate in Project Management exam
Question #: 67
Topic #: 3
[All Certified Associate in Project Management Questions]

The table represents the possible durations of a specific project task.

Using the three-point estimating technique what is the expected number of days it should take to complete the task?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Kris
12 days ago
I think I've got it! The expected duration should be 4 days. The formula makes sense, and it seems to match the information given in the question. This is a great way to estimate task durations when we don't have a lot of historical data to work with.
upvoted 0 times
Willie
10 hours ago
I chose 4 too. The formula really helps make sense of it.
upvoted 0 times
...
...
Paris
13 days ago
Haha, yeah, it's like we're all trying to be the next Nostradamus here. But hey, at least we're learning something useful, even if it's a bit of a brain-teaser. I'm sticking with 4 days as well.
upvoted 0 times
...
Avery
14 days ago
Okay, okay, I think I've got it now. The three-point estimating technique is like trying to hit a moving target with a blindfold on - it's a bit of a gamble, but it's better than just guessing, right? I'm going with 4 days too.
upvoted 0 times
...
Jacqueline
15 days ago
Wow, this is a tricky one! The three-point estimating technique is something we've been studying, but applying it to a real-world scenario can be challenging.
upvoted 0 times
...

Save Cancel