New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI CAPM Exam - Topic 2 Question 37 Discussion

Actual exam question for PMI's CAPM exam
Question #: 37
Topic #: 2
[All CAPM Questions]

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Annabelle
4 months ago
I’m with Sarah, 11 weeks makes sense!
upvoted 0 times
...
Arlette
4 months ago
C is definitely wrong, it’s longer than that.
upvoted 0 times
...
Brice
4 months ago
Wait, how does it add up to 10 weeks?
upvoted 0 times
...
Emogene
4 months ago
I think it’s 11 weeks, seems right!
upvoted 0 times
...
Alberto
4 months ago
Activity A + B = 4 weeks total.
upvoted 0 times
...
Shalon
5 months ago
I think I practiced a question like this, and it was about summing the durations of dependent activities. So maybe it's ten weeks?
upvoted 0 times
...
Rodolfo
5 months ago
I feel like it might be eleven weeks, but I can't quite remember if I counted everything correctly.
upvoted 0 times
...
Wilburn
5 months ago
I remember a similar question where we had to find the critical path. If Activity D is dependent on C, then we need to add all the times leading up to it.
upvoted 0 times
...
Alpha
5 months ago
I think the total time should be the longest path through the activities, but I'm not sure how to calculate that exactly.
upvoted 0 times
...
Cruz
5 months ago
Hmm, I'm a little unsure about this one. I think the scrum master should alert the team about the potential sprint goal issues, but I'm not sure if they should create an alternative plan or just let the team decide.
upvoted 0 times
...
Marva
5 months ago
I'm a little confused by the wording of these options. I know Agile and Scrum are connected, but I'm not sure I fully understand how. I'll have to re-read the question and choices carefully.
upvoted 0 times
...
Ellen
5 months ago
I practiced a question similar to this, and it highlighted that a conservative approach often leads to higher liquidity, but I can't recall if it affects permanent working capital directly.
upvoted 0 times
...
Eladia
5 months ago
This seems like a straightforward question. I'd recommend assigning one computer to each group so they can work on their project together.
upvoted 0 times
...

Save Cancel