PMI CAPM Exam - Topic 2 Question 11 Discussion
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.Which strategies should the project manager take into account for risk management in this environment?
D) Frequently review incremental work products and update the requirements for proper prioritization.
A) Occasionally identify, evaluate, and classify risks.
B) Review requirements and cross-functional project teams.
C) Include contingency reserves and update the project management plan frequently.