PMI CAPM Exam - Topic 2 Question 107 Discussion

Posted by Brittni on Mar 06, 2026 at 03:18 PM

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

Suggested Answer: A

Get Premium CAPM Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
31 comments · newest first
CA
Camellia 1 month ago
But B) is more about how to manage, not what to compare. A) is definitely the right choice.
LA
Latrice 1 month ago
I’m not so sure. What about B) Scope management plan? It guides the process.
AL
Alaine 2 months ago
I agree, A) Scope baseline is key for tracking changes.
MA
Markus 2 months ago
I think it's A) Scope baseline. It makes sense to compare planned vs actual.
WI
William 2 months ago
Definitely A) Scope baseline. It shows what was originally planned.
TH
Theola 2 months ago
I'm torn between A and B. But I lean towards A.
ES
Essie 2 months ago
I agree, A) Scope baseline is key for tracking changes.
BO
Bok 2 months ago
I think it's A) Scope baseline. It makes sense to compare planned vs actual.
JE
Jerry 3 months ago
But the scope baseline is the actual measure against results. It’s crucial!
BL
Blondell 3 months ago
I’m not so sure. What about B) Scope management plan? It guides the process.
LA
Lashawn 3 months ago
Agreed! Without the scope baseline, how do we know if we're on track?
SH
Shoshana 3 months ago
I think it's A) Scope baseline. It sets the standard.
GE
Geoffrey 3 months ago
Nope, it's not D) Cost baseline, that's for sure!
GW
Gwenn 3 months ago
Wait, is it really just the scope baseline? Seems too simple.
MI
Misty 4 months ago
A makes the most sense to me!
HU
Huey 4 months ago
I thought it was B) Scope management plan.
EL
Elroy 4 months ago
It's definitely A) Scope baseline.
GR
Gretchen 4 months ago
I disagree, I think it's D) Cost baseline.
LE
Lenna 4 months ago
Wait, is it really just the scope baseline? Sounds too simple.
VI
Viola 6 months ago
A) Scope baseline makes the most sense.
BE
Bettina 6 months ago
I thought it was B) Scope management plan?
AN
Andra 6 months ago
It's definitely A) Scope baseline.
JU
Justine 6 months ago
No way it's D) Cost baseline, that's for budgets, not scope!
MA
Marci 7 months ago
Wait, is it really just the scope baseline? Seems too simple.
LI
Lisbeth 7 months ago
A) Scope baseline makes the most sense!
DE
Dean 7 months ago
I thought it was B) Scope management plan.
MA
Maryrose 7 months ago
It's definitely A) Scope baseline.
TA
Tamesha 7 months ago
I’m confused because I thought the cost baseline was also important for performance measurement. Is it really A) Scope baseline?
AL
Alexia 7 months ago
I feel like I’ve seen a similar question before, and it was about the scope baseline too. So I’m leaning towards A) Scope baseline.
JA
Jamal 8 months ago
I’m not entirely sure, but I remember something about comparing actual results to a baseline. Could it be B) Scope management plan?
CA
Carman 8 months ago
I think the answer might be A) Scope baseline since it’s what we use to measure project performance against the planned scope.