For a 10-day project, activity B ' s duration is three days, and activity C's duration is two days What is the duration of activity A if activities B and C are performed in parallel?
For a 10-day project, activity B ' s duration is three days, and activity C's duration is two days What is the duration of activity A if activities B and C are performed in parallel?
I think I've got it! Since B and C are done in parallel, the total duration of the project is the maximum of their durations, which is 3 days for B. So the duration of A must be 3 days as well. I'll go with A) 3 days.
Hmm, this is tricky. I'm not sure if the parallel nature of B and C affects the duration of A or not. I'll have to think about this a bit more before answering.
Okay, let me think this through. The project is 10 days total, and activities B and C are done in parallel, so the duration of A must be the longest of the three, which is 3 days for activity B. I'll go with A) 3 days.
I'm a bit confused. If activities B and C are performed in parallel, shouldn't the duration of activity A be the maximum of the two, which is 3 days? I'm not sure about this one.
Hmm, this seems straightforward. I think I'll go with B) 5 days since the project is 10 days and the other two activities take 3 and 2 days respectively.
Viola
5 months agoEura
5 months agoMaybelle
5 months agoTimothy
5 months agoCatalina
6 months agoCecil
6 months agoRosendo
6 months agoBeckie
6 months agoCheryl
7 months agoLeila
7 months agoOliva
7 months agoLashonda
7 months agoKandis
7 months agoDiane
8 months agoNettie
8 months agoFrank
8 months agoSueann
8 months agoBritt
8 months agoNobuko
8 months agoKenneth
9 months agoBrice
9 months agoBette
9 months agoLajuana
9 months agoKaycee
10 months agoKaycee
10 months agoRanee
10 months agoZachary
4 months agoMargot
4 months agoCorinne
5 months agoNieves
5 months agoBlair
9 months ago