For a 10-day project, activity B ' s duration is three days, and activity C's duration is two days What is the duration of activity A if activities B and C are performed in parallel?
I think I've got it! Since B and C are done in parallel, the total duration of the project is the maximum of their durations, which is 3 days for B. So the duration of A must be 3 days as well. I'll go with A) 3 days.
Hmm, this is tricky. I'm not sure if the parallel nature of B and C affects the duration of A or not. I'll have to think about this a bit more before answering.
Okay, let me think this through. The project is 10 days total, and activities B and C are done in parallel, so the duration of A must be the longest of the three, which is 3 days for activity B. I'll go with A) 3 days.
I'm a bit confused. If activities B and C are performed in parallel, shouldn't the duration of activity A be the maximum of the two, which is 3 days? I'm not sure about this one.
Hmm, this seems straightforward. I think I'll go with B) 5 days since the project is 10 days and the other two activities take 3 and 2 days respectively.
Cheryl
15 hours agoLeila
6 days agoOliva
11 days agoLashonda
16 days agoKandis
21 days agoDiane
26 days agoNettie
1 month agoFrank
1 month agoSueann
1 month agoBritt
2 months agoNobuko
2 months agoKenneth
2 months agoBrice
2 months agoBette
2 months agoLajuana
2 months agoKaycee
3 months agoKaycee
3 months agoRanee
3 months agoBlair
3 months ago