For a 10-day project, activity B ' s duration is three days, and activity C's duration is two days What is the duration of activity A if activities B and C are performed in parallel?
I think I've got it! Since B and C are done in parallel, the total duration of the project is the maximum of their durations, which is 3 days for B. So the duration of A must be 3 days as well. I'll go with A) 3 days.
Hmm, this is tricky. I'm not sure if the parallel nature of B and C affects the duration of A or not. I'll have to think about this a bit more before answering.
Okay, let me think this through. The project is 10 days total, and activities B and C are done in parallel, so the duration of A must be the longest of the three, which is 3 days for activity B. I'll go with A) 3 days.
I'm a bit confused. If activities B and C are performed in parallel, shouldn't the duration of activity A be the maximum of the two, which is 3 days? I'm not sure about this one.
Hmm, this seems straightforward. I think I'll go with B) 5 days since the project is 10 days and the other two activities take 3 and 2 days respectively.
Viola
Eura
5 days agoMaybelle
10 days agoTimothy
15 days agoCatalina
21 days agoCecil
26 days agoRosendo
1 month agoBeckie
1 month agoCheryl
2 months agoLeila
2 months agoOliva
2 months agoLashonda
2 months agoKandis
3 months agoDiane
3 months agoNettie
3 months agoFrank
3 months agoSueann
3 months agoBritt
3 months agoNobuko
4 months agoKenneth
4 months agoBrice
4 months agoBette
4 months agoLajuana
4 months agoKaycee
5 months agoKaycee
5 months agoRanee
5 months agoBlair
5 months ago