Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI CAPM Exam - Topic 2 Question 104 Discussion

Actual exam question for PMI's CAPM exam
Question #: 104
Topic #: 2
[All CAPM Questions]

For a 10-day project, activity B ' s duration is three days, and activity C's duration is two days What is the duration of activity A if activities B and C are performed in parallel?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
10 days is way off, it's parallel work!
upvoted 0 times
...
Eura
5 days ago
I agree, 3 days makes sense.
upvoted 0 times
...
Maybelle
10 days ago
7 days seems too long for A.
upvoted 0 times
...
Timothy
15 days ago
Definitely 3 days, B and C overlap.
upvoted 0 times
...
Catalina
21 days ago
I feel like it could be 5 days.
upvoted 0 times
...
Cecil
26 days ago
Definitely 3 days, no doubt about it!
upvoted 0 times
...
Rosendo
1 month ago
I think it's actually 5 days, right?
upvoted 0 times
...
Beckie
1 month ago
A should be 3 days since B and C are parallel.
upvoted 0 times
...
Cheryl
2 months ago
Wait, is this a trick question? I'm so confused, but I'll go with B) 5 days. Sounds like the most reasonable answer.
upvoted 0 times
...
Leila
2 months ago
Haha, this question is a real brain-teaser. I'm going to go with C) 7 days, just to be on the safe side.
upvoted 0 times
...
Oliva
2 months ago
A) 3 days. The question is a trick! Since B and C are done in parallel, the duration of A must be the longest of the three, which is 3 days.
upvoted 0 times
...
Lashonda
2 months ago
D) 10 days. If the project duration is 10 days and the other two activities are done in parallel, then activity A must take the full 10 days.
upvoted 0 times
...
Kandis
3 months ago
C) 7 days. The question states that activities B and C are performed in parallel, so the duration of A must be the remaining time.
upvoted 0 times
...
Diane
3 months ago
B) 5 days. Seems logical since the project duration is 10 days and the other two activities take 5 days in total.
upvoted 0 times
...
Nettie
3 months ago
I’m leaning towards 7 days for A because it seems like it needs to account for both B and C somehow, but I’m not entirely confident.
upvoted 0 times
...
Frank
3 months ago
I practiced a similar question where parallel tasks didn't add up directly. I feel like A could be 5 days, but I could be wrong.
upvoted 0 times
...
Sueann
3 months ago
I remember something about adding durations when activities are in series, but since B and C are parallel, I’m not sure how that affects A.
upvoted 0 times
...
Britt
3 months ago
I think if B and C are done in parallel, A's duration might depend on the longest one, which is B at 3 days?
upvoted 0 times
...
Nobuko
4 months ago
I think I've got it! Since B and C are done in parallel, the total duration of the project is the maximum of their durations, which is 3 days for B. So the duration of A must be 3 days as well. I'll go with A) 3 days.
upvoted 0 times
...
Kenneth
4 months ago
Hmm, this is tricky. I'm not sure if the parallel nature of B and C affects the duration of A or not. I'll have to think about this a bit more before answering.
upvoted 0 times
...
Brice
4 months ago
Activity B takes 3 days, C takes 2 days.
upvoted 0 times
...
Bette
4 months ago
Okay, let me think this through. The project is 10 days total, and activities B and C are done in parallel, so the duration of A must be the longest of the three, which is 3 days for activity B. I'll go with A) 3 days.
upvoted 0 times
...
Lajuana
4 months ago
I think it's 3 days.
upvoted 0 times
...
Kaycee
5 months ago
Wait, is it really just 3 days? That seems too short!
upvoted 0 times
...
Kaycee
5 months ago
I'm a bit confused. If activities B and C are performed in parallel, shouldn't the duration of activity A be the maximum of the two, which is 3 days? I'm not sure about this one.
upvoted 0 times
...
Ranee
5 months ago
Hmm, this seems straightforward. I think I'll go with B) 5 days since the project is 10 days and the other two activities take 3 and 2 days respectively.
upvoted 0 times
Blair
5 months ago
Why do you think that? B and C are happening at the same time.
upvoted 0 times
...
...

Save Cancel