Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam CAPM Topic 1 Question 96 Discussion

Actual exam question for PMI's CAPM exam
Question #: 96
Topic #: 1
[All CAPM Questions]

Which of the following are three inputs to the risk register?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Derick
14 days ago
I'm not sure about that. I think B might be the right answer, with the communication management plan, enterprise environmental factors, and activity duration estimates.
upvoted 0 times
...
Junita
18 days ago
I think the correct answer is C. The risk management plan, activity cost estimates, and project documents are the inputs to the risk register.
upvoted 0 times
Olive
2 days ago
I think the correct answer is C.
upvoted 0 times
...
Yasuko
3 days ago
Great job! It's important to understand the inputs to the risk register for effective project management.
upvoted 0 times
...
My
5 days ago
Yes, you are right. The risk management plan, activity cost estimates, and project documents are indeed inputs to the risk register.
upvoted 0 times
...
Bernardo
7 days ago
I think the correct answer is C.
upvoted 0 times
...
...

Save Cancel