New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI CAPM Exam - Topic 1 Question 96 Discussion

Actual exam question for PMI's CAPM exam
Question #: 96
Topic #: 1
[All CAPM Questions]

Which of the following are three inputs to the risk register?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Lashawn
2 months ago
I agree with C, but A has some good points too!
upvoted 0 times
...
Helene
2 months ago
Wait, are we sure about C? Seems off to me.
upvoted 0 times
...
Jeannetta
3 months ago
No way, it's B for sure!
upvoted 0 times
...
Tyra
3 months ago
I thought it was A at first, but C makes more sense.
upvoted 0 times
...
Angelica
3 months ago
Definitely C! Those are key inputs.
upvoted 0 times
...
Tamra
3 months ago
I feel like the project scope statement could be relevant, but I don't remember it being a direct input to the risk register.
upvoted 0 times
...
Reyes
4 months ago
I’m torn between options A and C. I know the risk management plan is key, but I can't recall the other inputs clearly.
upvoted 0 times
...
Glendora
4 months ago
I remember practicing a question about inputs to the risk register, and I feel like the stakeholder register was mentioned there too.
upvoted 0 times
...
Alberto
4 months ago
I think the risk management plan is definitely an input, but I'm not sure about the other two.
upvoted 0 times
...
Chantell
4 months ago
I've got this! The key inputs are the risk management plan, which outlines the risk management approach, the stakeholder register, which identifies key stakeholders and their risk tolerances, and the quality management plan, which covers quality-related risks.
upvoted 0 times
...
Nina
4 months ago
Okay, let me think this through. The risk register captures all the identified risks, so the inputs must be things like the risk management plan and any project documents that contain risk information.
upvoted 0 times
...
Elly
5 months ago
Hmm, I'm a bit unsure about this one. I know the risk register is an important tool, but I can't quite remember all the specific inputs off the top of my head.
upvoted 0 times
...
Julio
5 months ago
This looks like a straightforward question about the risk register. I'll need to recall the key inputs to the risk register process.
upvoted 0 times
...
Terry
8 months ago
Risk register? More like 'risk amusement park'! But seriously, I think the answer is C.
upvoted 0 times
Flo
7 months ago
I agree with you, it's definitely C.
upvoted 0 times
...
Jerry
7 months ago
I'm pretty sure it's D.
upvoted 0 times
...
Lynda
7 months ago
No, I believe it's A.
upvoted 0 times
...
Kip
7 months ago
No, it's actually A. Risk register updates, stakeholder register, and quality management plan are inputs.
upvoted 0 times
...
Isreal
8 months ago
I think the answer is C.
upvoted 0 times
...
Kristin
8 months ago
I think the answer is C.
upvoted 0 times
...
...
Corrie
8 months ago
I see your point, Deeanna. It's important to consider all the options before making a final decision.
upvoted 0 times
...
Deeanna
8 months ago
I'm not sure, but I think D) Project scope statement, organizational process assets, and scope baseline could also be inputs to the risk register.
upvoted 0 times
...
Bethanie
9 months ago
I disagree, I believe the correct answer is C) Risk management plan, activity cost estimates, and project documents.
upvoted 0 times
...
Corrie
9 months ago
I think the answer is A) Risk register updates, stakeholder register, and quality management plan.
upvoted 0 times
...
Afton
9 months ago
Haha, this is a tricky one! I'm going to go with D just to see if I can throw the grader off.
upvoted 0 times
Gilberto
8 months ago
User 3: I'm going with D just to mix things up.
upvoted 0 times
...
Sue
8 months ago
User 2: I believe it's A.
upvoted 0 times
...
Mammie
8 months ago
User 1: I think the answer is C.
upvoted 0 times
...
...
Derick
10 months ago
I'm not sure about that. I think B might be the right answer, with the communication management plan, enterprise environmental factors, and activity duration estimates.
upvoted 0 times
...
Junita
10 months ago
I think the correct answer is C. The risk management plan, activity cost estimates, and project documents are the inputs to the risk register.
upvoted 0 times
Leonor
9 months ago
That makes sense. Those inputs are crucial for identifying and analyzing risks.
upvoted 0 times
...
Maryln
9 months ago
The risk management plan, activity cost estimates, and project documents are the inputs to the risk register.
upvoted 0 times
...
Olive
9 months ago
I think the correct answer is C.
upvoted 0 times
...
Yasuko
9 months ago
Great job! It's important to understand the inputs to the risk register for effective project management.
upvoted 0 times
...
My
9 months ago
Yes, you are right. The risk management plan, activity cost estimates, and project documents are indeed inputs to the risk register.
upvoted 0 times
...
Bernardo
9 months ago
I think the correct answer is C.
upvoted 0 times
...
...

Save Cancel