Which of the following is an example of an internal factor that influences the outcome of the project?

Show Suggested Answer Hide Answer
Suggested Answer: D

(Geographic distribution of facilities and resources) EEFs internal to the organization pg 76 of 6th Edition. All other options are listed under the EEFs External to the organization