Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PeopleCert Exam PRINCE2 Agile Practitioner Topic 5 Question 15 Discussion

Actual exam question for PeopleCert's PRINCE2 Agile Practitioner exam
Question #: 15
Topic #: 5
[All PRINCE2 Agile Practitioner Questions]

Which is consistent with the eight guidance points of PRINCE2 Agile?

Show Suggested Answer Hide Answer
Suggested Answer: B

This highlights that while Scrum and Kanban have their own roles and frameworks, the role of the project manager can still exist and be integrated within Agile practices, including PRINCE2 Agile.


Contribute your Thoughts:

Carma
7 days ago
D is the winner for me. A project manager is just a relic of the old 'command and control' way of doing things. Agile is all about empowering the team!
upvoted 0 times
...
Raymon
10 days ago
I see where both of you are coming from, but I personally think option D makes the most sense in this context.
upvoted 0 times
...
Lezlie
22 days ago
I disagree, I believe option C is more aligned with the principles of PRINCE2 Agile.
upvoted 0 times
...
Lorean
1 months ago
I think option B is consistent with the eight guidance points of PRINCE2 Agile.
upvoted 0 times
...
Erasmo
1 months ago
Option B seems the most accurate to me. Scrum and Kanban don't define the project manager role, but that doesn't mean it's not required.
upvoted 0 times
Luisa
20 hours ago
User 3: Working in an agile way doesn't necessarily remove the need for a project manager.
upvoted 0 times
...
Roselle
16 days ago
User 2: I agree, just because they don't define it doesn't mean it's not needed.
upvoted 0 times
...
Florinda
29 days ago
User 1: I think option B is correct. Scrum and Kanban don't define the project manager role.
upvoted 0 times
...
...

Save Cancel