Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PECB ISO-IEC-27001-Lead-Implementer Exam - Topic 5 Question 68 Discussion

Scenario 9: OpenTech provides IT and communications services. It helps data communication enterprises and network operators become multi-service providers During an internal audit, its internal auditor, Tim, has identified nonconformities related to the monitoring procedures He identified and evaluated several system Invulnerabilities.Tim found out that user IDs for systems and services that process sensitive information have been reused and the access control policy has not been followed After analyzing the root causes of this nonconformity, the ISMS project manager developed a list of possible actions to resolve the nonconformity. Then, the ISMS project manager analyzed the list and selected the activities that would allow the elimination of the root cause and the prevention of a similar situation in the future. These activities were included in an action plan The action plan, approved by the top management, was written as follows:A new version of the access control policy will be established and new restrictions will be created to ensure that network access is effectively managed and monitored by the Information and Communication Technology (ICT) DepartmentThe approved action plan was implemented and all actions described in the plan were documented.Based on scenario 9. did the ISMS project manager complete the corrective action process appropriately?
C) No, the corrective action process should also include the review of the implementation of the selected actions
A) Yes, the corrective action process should include the identification of the nonconformity, situation analysis, and implementation of corrective actions
B) No, the corrective action did not address the root cause of the nonconformity

PECB ISO-IEC-27001-Lead-Implementer Exam - Topic 5 Question 68 Discussion

Actual exam question for PECB's ISO-IEC-27001-Lead-Implementer exam
Question #: 68
Topic #: 5
[All ISO-IEC-27001-Lead-Implementer Questions]

Scenario 9: OpenTech provides IT and communications services. It helps data communication enterprises and network operators become multi-service providers During an internal audit, its internal auditor, Tim, has identified nonconformities related to the monitoring procedures He identified and evaluated several system Invulnerabilities.

Tim found out that user IDs for systems and services that process sensitive information have been reused and the access control policy has not been followed After analyzing the root causes of this nonconformity, the ISMS project manager developed a list of possible actions to resolve the nonconformity. Then, the ISMS project manager analyzed the list and selected the activities that would allow the elimination of the root cause and the prevention of a similar situation in the future. These activities were included in an action plan The action plan, approved by the top management, was written as follows:

A new version of the access control policy will be established and new restrictions will be created to ensure that network access is effectively managed and monitored by the Information and Communication Technology (ICT) Department

The approved action plan was implemented and all actions described in the plan were documented.

Based on scenario 9. did the ISMS project manager complete the corrective action process appropriately?

Show Suggested Answer Hide Answer
Suggested Answer: C

According to ISO/IEC 27001:2022, the corrective action process consists of the following steps12:

Reacting to the nonconformity and, as applicable, taking action to control and correct it and deal with the consequences

Evaluating the need for action to eliminate the root cause(s) of the nonconformity, in order that it does not recur or occur elsewhere

Implementing the action needed

Reviewing the effectiveness of the corrective action taken

Making changes to the information security management system, if necessary

In scenario 9, the ISMS project manager did not complete the last step of reviewing the effectiveness of the corrective action taken. This step is important to verify that the corrective action has achieved the intended results and that no adverse effects have been introduced.The review can be done by using various methods, such as audits, tests, inspections, or performance indicators3. Therefore, the ISMS project manager did not complete the corrective action process appropriately.

1:ISO/IEC 27001:2022, clause 10.22:Procedure for Corrective Action [ISO 27001 templates]3:ISO 27001 Clause 10.2 Nonconformity and corrective action


Contribute your Thoughts:

0/2000 characters
Beth
7 hours ago
Wait, they reused user IDs? That's a huge red flag!
upvoted 0 times
...
Wilda
5 days ago
I think they missed reviewing the implementation part.
upvoted 0 times
...
Clarence
11 days ago
Sounds like they followed the steps right.
upvoted 0 times
...
Edison
16 days ago
I thought the corrective action process should include follow-up reviews to ensure everything is working as intended. That seems like a gap in this scenario.
upvoted 0 times
...
Cassi
2 months ago
I feel like just having a new access control policy isn't enough. The root cause needs to be tackled more directly, right?
upvoted 0 times
...
Jules
2 months ago
I remember a practice question that emphasized the importance of reviewing the implementation of corrective actions. That might be a missing step here.
upvoted 0 times
...
Joye
2 months ago
I think the ISMS project manager did a good job identifying the nonconformity and creating an action plan, but I'm not sure if they fully addressed the root cause.
upvoted 0 times
...

Save Cancel