Here you can find all the free questions related with NCARB ARE 5.0 Project Management (PjM) Exam (Project-Management) exam. You can also find on this page links to recently updated premium files with which you can practice for actual NCARB ARE 5.0 Project Management (PjM) Exam . These premium versions are provided as Project-Management exam practice tests, both as desktop software and browser based application, you can use whatever suits your style. Feel free to try the ARE 5.0 Project Management (PjM) Exam premium files for free, Good luck with your NCARB ARE 5.0 Project Management (PjM) Exam .
Question No: 1
MultipleChoice
The owner and architect sign a Basic Services Agreement for the design of a museum.
Based on AIA Document B101-2017, Owner and Architect Agreement, which line items should be excluded from the architect's cost estimate? Check the two that apply.
Options
Answer C, EExplanation
Per AIA B101-2017 6.1, the 'Cost of the Work' includes items designed or specified by the architect in the construction contract. FF&E and owner-provided landscape features (like plants, art, and loose furniture) are typically excluded, as these may be contracted separately by the owner or coordinated outside basic architectural services.