NCARB Project-Management Exam - Topic 1 Question 19 Discussion

Refer to the exhibit.Refer to the exhibit.Construction documents are 75% complete for a design-bid-build project. As part of an architecture firm's quality control plan, the senior architect reviews the drawings and specifications for coordination. Following the review, the project architect distributes the senior architect's markups to the consultants.What should the mechanical engineer do next to maintain quality control?
C) Request a redline work session with the project architect to discuss the floor plan
A) Request a fire rating review with the senior architect
B) Request a constructability review of the ductwork with the project team

NCARB Project-Management Exam - Topic 1 Question 19 Discussion

Actual exam question for NCARB's Project-Management exam
Question #: 19
Topic #: 1
[All Project-Management Questions]

Refer to the exhibit.

Refer to the exhibit.

Construction documents are 75% complete for a design-bid-build project. As part of an architecture firm's quality control plan, the senior architect reviews the drawings and specifications for coordination. Following the review, the project architect distributes the senior architect's markups to the consultants.

What should the mechanical engineer do next to maintain quality control?

Show Suggested Answer Hide Answer
Suggested Answer: C

The mechanical engineer is responsible for responding to coordination markups---such as conflicts between ductwork and fire-rated walls, dampers, or structural components. By requesting a redline work session, the mechanical engineer can collaborate directly with the project architect to resolve spatial, code, and fire protection conflicts, ensuring the integrity of both mechanical systems and building code compliance.

This action aligns with best practices in Quality Control/Assurance (QA/QC) procedures, where inter-disciplinary coordination during the Construction Documents (CD) phase is essential to reduce RFIs and change orders later.

ARE 5.0 PjM Reference:

NCARB ARE 5.0 Handbook -- PjM: 'Coordination of drawings and consultant input during documentation'

AIA Best Practices: Consultant collaboration and redline review during CD phase

AHPP (Architect's Handbook of Professional Practice), 15th ed., Chapter 9: Quality Management


Contribute your Thoughts:

0/2000 characters
Aileen
4 days ago
I practiced a similar question where we had to decide on the next steps after a review, and I feel like discussing the floor plan could be crucial.
upvoted 0 times
...
Valentin
9 days ago
I think a constructability review could help identify any issues early on, but I’m not entirely confident if that’s what’s needed right now.