Question #: 11
Topic #: 1
[All Project-Management Questions]

Which of the following is a key advantage of using Building Information Modeling (BIM)?

Show Suggested Answer Hide Answer
Suggested Answer: B

BIM facilitates integrated coordination of multiple disciplines by enabling a shared digital model, reducing conflicts, improving visualization, and enhancing collaboration. It supports clash detection and improves efficiency but does not eliminate construction documents or replace contractors. ARE 5.0 PjM emphasizes technology's role in project delivery.


Contribute your Thoughts:

0/2000 characters
Juan
4 days ago
I feel like there was a practice question that mentioned cost savings, but I’m not convinced it guarantees them.
upvoted 0 times
...
Adell
9 days ago
I’m not entirely sure, but I remember something about BIM not eliminating the need for construction documents.
upvoted 0 times
...
Cherelle
14 days ago
I think BIM really helps with coordination, especially between different systems like MEP and structural elements.
upvoted 0 times
...

Save Cancel