A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.
The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view.
You need to configure the system to meet the requirements.
Which three options should you configure? Each answer presents a partial solution.
NOTE: Each correct selection is worth one point.
Erick
1 months agoFabiola
1 months agoAlonzo
1 months agoEleni
3 days agoParis
4 days agoRuthann
27 days agoBenton
2 months agoMaryanne
5 days agoNichelle
16 days agoMerissa
30 days agoNichelle
1 months agoCorazon
1 months agoTenesha
2 months agoWhitney
2 months agoLinwood
2 months agoToi
2 months ago