Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft Exam 74-343 Topic 1 Question 5 Discussion

Actual exam question for Microsoft's 74-343 exam
Question #: 5
Topic #: 1
[All 74-343 Questions]

You manage a project by using Project Professional 2013. Your project is updated with changes to the baseline for selected tasks.

You back up your project fife before you start your next tracking cycle. After completing the tracking cycle, you notice that the baseline duration values on some of the summary tasks are not correct.

You need to correct these values before re-entering the tracking data.

You open the backed up version of the project schedule.

What should you do next?

Show Suggested Answer Hide Answer
Suggested Answer: D

Comments

Currently there are no comments in this discussion, be the first to comment!


Save Cancel