Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft 74-343 Exam

Status: RETIRED
Certification Provider: Microsoft
Exam Name: Managing Projects with Microsoft Project
Duration: 90 Minutes
Number of questions in our database: 109
Exam Version: 25-06-2019
74-343 Exam Official Topics:
  • Topic 1: Initialize a project Manage resources and assignments Communicate project information
Disscuss Microsoft 74-343 Topics, Questions or Ask Anything Related

Currently there are no comments in this discussion, be the first to comment!

Free Microsoft 74-343 Exam Actual Questions

The questions for 74-343 were last updated On 25-06-2019

Question #1

You manage a project by using Project Professional 2013. Your project is updated with changes to the baseline for selected tasks.

You back up your project fife before you start your next tracking cycle. After completing the tracking cycle, you notice that the baseline duration values on some of the summary tasks are not correct.

You need to correct these values before re-entering the tracking data.

You open the backed up version of the project schedule.

What should you do next?

Reveal Solution Hide Solution
Correct Answer: D

Question #2

You are a program manager. Your project managers use Project Professional 2013 to manage projects. The project managers want to utilize the same resources across their projects.

You need to combine the projects, as well as the project resources, to see allocations across the projects.

What should you do?

Reveal Solution Hide Solution
Correct Answer: B

Question #3

Your company uses Project Standard 2013 to track project progress.

You need to accurately calculate cost performance index (CPI) as a health indicator.

Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

Reveal Solution Hide Solution
Correct Answer: A, B, D

Question #4

You create a new schedule by using Microsoft Project. All calendars and working hours use default settings. You configure the schedule to show all assignment units as decimal values.

A resource reports a reduction in availability for your project by two hours per day.

You need to update the project to reflect the availability of the resource.

What are two possible ways to achieve the goal? Each correct answer presents a complete solution.

Reveal Solution Hide Solution
Question #5

You update a schedule that you are managing by using Microsoft Project.

After the update, you observe that many of the resources in the schedule are overallocated.

You need to resource level the schedule without changing the current projected finish data for the project.

Which three actions will achieve the goal? Each correct answer presents part of the solution.

Reveal Solution Hide Solution
Correct Answer: B, C, E

References:

https://support.office.com/en-us/article/Level-resource-assignments-49fb52d5-ff4a-4b1f-b5c1-af057ab38ba2

http://www.dummies.com/software/microsoft-office/project/how-to-level-resources-in-project-2013/



Unlock all 74-343 Exam Questions with Advanced Practice Test Features:
  • Select Question Types you want
  • Set your Desired Pass Percentage
  • Allocate Time (Hours : Minutes)
  • Create Multiple Practice tests with Limited Questions
  • Customer Support
Get Full Access Now

Save Cancel