ISTQB ATM Exam - Topic 2 Question 86 Discussion

In the next two months some new features will be constantly added to new releases of a project you are working on as Test Manager.You have identified as one of the main project risks, that the requirements specification will still be incomplete when your team starts the test design and implementation phase.Some requirements will most likely be completed too late to allow a proper test preparation. You and your test team have already worked on several similar past projects in the same organization.Which one of the following options would you expect to be the most effective at mitigating this risk?K4 3 credits
B) Make reasonable assumptions about the missing details and design lightweight tests that can be easily updated during test execution
A) Don't prepare any test and just run the regression test suite to check that the new features don't introduce regression
C) Don't design any test until the test execution starts, then communicate that test execution is blocked due to incomplete requirements
D) Even if there are only few details missing, escalate the risk to the project manager without preparing any tests

ISTQB ATM Exam - Topic 2 Question 86 Discussion

Actual exam question for ISTQB's ATM exam
Question #: 86
Topic #: 2
[All ATM Questions]

In the next two months some new features will be constantly added to new releases of a project you are working on as Test Manager.

You have identified as one of the main project risks, that the requirements specification will still be incomplete when your team starts the test design and implementation phase.

Some requirements will most likely be completed too late to allow a proper test preparation. You and your test team have already worked on several similar past projects in the same organization.

Which one of the following options would you expect to be the most effective at mitigating this risk?

K4 3 credits

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
I’m torn between B and D. While I see the value in escalating risks, I wonder if we’d be better off preparing something flexible like in option B.
upvoted 0 times
...
Johnna
5 days ago
I practiced a question about risk management last week, and I think option A could leave us vulnerable. We can't just rely on regression tests without proper test cases.
upvoted 0 times
...
Merilyn
10 days ago
I think we've encountered similar scenarios before where incomplete requirements led to delays. I feel like option D might just escalate tensions without providing a solution.
upvoted 0 times
...
Nikita
15 days ago
I remember discussing the importance of being proactive in test design, so option B seems like a reasonable approach, but I'm not entirely sure if making assumptions is always safe.
upvoted 0 times
...

Save Cancel