ISTQB ATM Exam - Topic 1 Question 82 Discussion
Which of the following is an example of the test closure activity indicated as "lessons learned"? K2 1 credit
C) Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
A) Archive all the test results of the acceptance testing phase
B) Deliver a list of the open defects of a software product released into production to the service desk team
D) Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing