You are managing the system testing for a SOA based system. The integrated system consists of several subsystems:
- A SOA middleware
- A CRM (Customer Relationship Management) system
- A BRM (Billing and Revenue Management) system
- A SMS (Subscriber Management System) system and you performed a risk analysis based on these subsystems.

At the end of the scheduled period for test execution you produce a first classical report based on the traditional metrics of testing. Test pass/fail status and bug status (open/resolved) That table provides you a distorted picture of the quality risk, because there is no indication of the risk level of the failed tests, the tests not run, or the open bugs. Thus, you produce the following table to solve this distortion issue:
In the table above, where you have introduced the concept of risk weighting, the highest risk test or bug report has a score of 1, while the lowest risk test or bug report has a score of 0.04. Which of the following subsystems, based on the risk scores of the table, is most risky? K4 3 credits
Bulah
4 months agoNickolas
4 months agoCarey
4 months agoMaurine
4 months agoViola
4 months agoAlba
5 months agoBillye
5 months agoDorthy
5 months agoWilletta
5 months agoBrande
5 months agoYoulanda
5 months agoPrecious
5 months agoDelila
5 months agoMaxima
9 months agoTrinidad
8 months agoKimbery
9 months agoPhil
9 months agoHerminia
10 months agoShasta
8 months agoCyndy
9 months agoFranchesca
9 months agoDeane
9 months agoThurman
10 months agoKarma
10 months agoFranklyn
8 months agoGennie
8 months agoTresa
8 months agoFranchesca
8 months agoShaun
8 months agoFiliberto
8 months agoJillian
9 months agoBenedict
9 months agoRoselle
10 months agoGearldine
11 months agoDahlia
11 months agoKristeen
9 months agoCruz
9 months agoMabel
9 months agoDelisa
9 months agoTyra
9 months agoTamesha
10 months agoCletus
10 months agoOmega
10 months agoRoselle
11 months ago