ISC2 ISSMP Exam - Topic 5 Question 93 Discussion

Actual exam question for ISC2's ISSMP exam
Question #: 93
Topic #: 5
[All ISSMP Questions]

You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Alverta
3 months ago
The risk register is standard for tracking risk responses and statuses.
upvoted 0 times
...
Raylene
3 months ago
Wait, are we sure it’s not the lessons learned documentation? Seems odd.
upvoted 0 times
...
Kanisha
3 months ago
I agree, the risk register is the best choice.
upvoted 0 times
...
Ethan
4 months ago
I think it should be in the risk management plan, right?
upvoted 0 times
...
Franklyn
4 months ago
Definitely the risk register! That's where all the details go.
upvoted 0 times
...
Roy
4 months ago
I’m a bit confused about the lessons learned documentation. I thought that was for after the project, not for current risk responses.
upvoted 0 times
...
Josefa
4 months ago
I feel like we practiced a question similar to this, and the risk register was definitely the answer. It makes sense to keep everything in one place.
upvoted 0 times
...
Alethea
4 months ago
I’m not entirely sure, but I remember something about the risk management plan being important too. Maybe it’s a part of that?
upvoted 0 times
...
Queenie
5 months ago
I think the risk register is where we should document the risk responses and their status, right? It’s where we track all identified risks.
upvoted 0 times
...
Gertude
5 months ago
Wait, I'm a little confused. Isn't the risk management plan also a place where we might document risk responses? Or could it be the lessons learned documentation? I want to make sure I fully understand where this information should be captured.
upvoted 0 times
...
Rebbecca
5 months ago
Okay, I think I've got this. The risk register is where we should be documenting the proposed risk responses and the current status of all identified risks. That makes the most sense to me based on what I've learned about project risk management.
upvoted 0 times
...
Jacki
5 months ago
Hmm, I'm a bit unsure on this one. I know the risk register is important for risk management, but I'm not totally sure if that's the only place we should document the proposed responses and current status. Let me think this through a bit more.
upvoted 0 times
...
Theola
5 months ago
This seems like a straightforward risk management question. I'm pretty confident the answer is the risk register, since that's where we typically document risk responses and status.
upvoted 0 times
...
Lacresha
10 months ago
The risk register, of course! Unless, of course, the risks are too scared to register themselves. Then we'll just have to chase them down and force them to sign up.
upvoted 0 times
Quentin
8 months ago
C) Risk register
upvoted 0 times
...
Carman
9 months ago
C) Risk register
upvoted 0 times
...
Viva
9 months ago
A) Risk management plan
upvoted 0 times
...
...
Bette
10 months ago
Wait, did someone say 'risk'? I thought this was a project to build a water slide park. Where's the risk in that?
upvoted 0 times
Gerald
8 months ago
C) Risk register
upvoted 0 times
...
Shawna
9 months ago
C) Risk register
upvoted 0 times
...
Dortha
9 months ago
A) Risk management plan
upvoted 0 times
...
Raina
9 months ago
C) Risk register
upvoted 0 times
...
Justine
9 months ago
C) Risk register
upvoted 0 times
...
Ronny
9 months ago
A) Risk management plan
upvoted 0 times
...
...
Karima
10 months ago
The risk management plan? Hmm, I guess that could work, but it seems a bit overkill. The risk register is the one-stop-shop for all things risk-related.
upvoted 0 times
...
Mauricio
10 months ago
Lessons learned? Really? That's for capturing the knowledge gained after the project, not during it. The risk register is the obvious choice here.
upvoted 0 times
...
Novella
10 months ago
I believe the risk management plan is also important to document the proposed responses for better management.
upvoted 0 times
...
Steffanie
10 months ago
I'm not sure why anyone would choose the stakeholder management strategy. That's for managing the stakeholders, not the risks!
upvoted 0 times
Alison
9 months ago
C) Risk register
upvoted 0 times
...
Michal
10 months ago
A) Risk management plan
upvoted 0 times
...
...
Sheron
11 months ago
The risk register is definitely where we should document the proposed responses and the current status of all identified risks. It's the central repository for all things risk-related in the project.
upvoted 0 times
...
Carin
11 months ago
I agree with Lashon. The risk register is the best place to track the status of identified risks.
upvoted 0 times
...
Lashon
11 months ago
I think we should document the proposed responses in the risk register.
upvoted 0 times
...

Save Cancel