When tailoring COBIT 2019 to enterprise requirements, which of the following is the PRIMARY objective of preparing a risk profile?
According to Isaca COBIT 2019, the primary objective of preparing a risk profile is to identify areas of risk that exceed the risk appetite of the enterprise. This involves assessing the potential risks that the enterprise is exposed to, and determining if these risks exceed the level of risk that the enterprise is willing to accept. This helps the enterprise understand and prioritize the areas of risk that need to be addressed, and helps to ensure that appropriate measures are taken to mitigate these risks.