An organization prefers to execute projects using an adaptive approach. However, the new project is much more complex than previously executed projects. What will the business analyst (BA) recommend?
Suggested Answer: C
Get Premium CCBA Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
Predictive approach: An approach where planning and baselines are established early in the life cycle of the initiative in order to maximize control and minimize risk.
11 comments · newest first
TO
Tomoko
1 year ago
Agile programming is definitely the way to go for complexity!
GI
Gilberto
1 year ago
Wait, why would they switch to a predictive approach? Seems risky!
LI
Linette
1 year ago
Extreme programming might be too much for complex projects.
MA
Marjory
1 year ago
Totally agree, stakeholder input is crucial!
TA
Tammi
1 year ago
I think reviewing the current approach is key.
GR
Graciela
1 year ago
Choosing an agile programming approach sounds familiar, but I wonder if it’s really the best fit for something more complex.
AL
Alyssa
1 year ago
I'm not entirely sure, but I feel like going for an extreme programming approach could be too risky for a complex project.
VE
Veta
1 year ago
I remember we discussed how adaptive approaches can be beneficial, but with increased complexity, it might be tricky.
CA
Carli
1 year ago
I think we practiced a similar question where the BA had to balance stakeholder needs with project complexity. Maybe reviewing the current approach is key?
AL
Alpha
1 year ago
This question seems pretty straightforward. I think the key is to focus on the differences between group healthcare and workers' compensation.
AL
Alyce
1 year ago
This looks like a straightforward question about managing Dynamics 365 for Field Service development. I think the key is to understand how the Woodford solution works and how to enable multiple developers to contribute to it.